55V. Determination of applications

(1) An application under this Part must be determined by the regulator to which it is required to be made ("the appropriate regulator") before the end of the period of 6 months beginning with the date on which it received the completed application.

(2) The appropriate regulator may determine an incomplete application if it considers it appropriate to do so; and it must in any event determine such an application within 12 months beginning with the date on which it received the application.

(3) Where the application cannot be determined by the appropriate regulator without the consent of the other regulator, the other regulator's decision must also be made within the period required by subsection (1) or (2).

(4) The applicant may withdraw the application, by giving the appropriate regulator written notice, at any time before the appropriate regulator determines it.

(5) If the appropriate regulator grants an application -

(a) for Part 4A permission,

(b) for the variation or cancellation o