Date-stamp loading
Version status: In force | Document consolidation status: Updated to reflect all known changes
Version date: 6 June 2013 - onwards
    Version 1 of 1    

261R. Procedure when refusing approval of a proposal under section 261Q

(1) If the FCA proposes to refuse approval of a proposal under section 261Q to replace the depositary or operator of an authorised contractual scheme, it must give a warning notice to the person by whom notice of the proposal was given under section 261Q(4) or (5).

(2) If the FCA proposes to refuse approval of a proposal under section 261Q to alter an authorised contractual scheme, it must give separate warning notices to the operator and the depositary of the scheme.

(3) To be valid the warning notice must be received by the person to whom it is given before the end of one month beginning with the date on which notice of the proposal was given.

(4) If, having given a warning notice to a person, the FCA decides to refuse approval -

(a) it must give that person a decision notice; and

(b) that person may refer the matter to the Tribunal.

Comparing proposed amendment...