Skip to main content
Version status: Entered into force | Document consolidation status: Updated to reflect all known changes
Version date: 17 April 2014 - onwards
Version 2 of 2

Article 28 Restricted procedure

1. In restricted procedures, any economic operator may submit a request to participate in response to a call for competition containing the information set out in Annex V parts B or C as the case may be by providing the information for qualitative selection that is requested by the contracting authority.

The minimum time limit for receipt of requests to participate shall be 30 days from the date on which the contract notice or, where a prior information notice is used as a means of calling for competition, the invitation to confirm interest was sent.

2. Only those economic operators invited to do so by the contracting authority following its assessment of the information provided may submit a tender. Contracting authorities may limit the number of suitable candidates to be invited to participate in the procedure in accordance with Article 65.

The minimum time limit for the receipt of tenders shall be 30 days from the date on which the invitation to tender was sent.

3. Where contracting authorities have published a prior information notice which was not itself used as a means of calling for competition, the minimum time limit for the receipt of tenders as laid down in the second subparagraph of paragraph 2 of this Article may be shortened to 10 days, provided that all of the following conditions are fulfilled: