Regulation 102 Transitional provision: pending applications for trade licences
(1) Paragraph (2) applies where -
(a) an application was made before IP completion day for a licence or authorisation under or pursuant to the Export Control Order 2008 or the Dual-Use Regulation,
(b) the application is for authorisation of an act prohibited by Part 5 (Trade), and
(c) a decision to grant or refuse the application has not been made before IP completion day.
(2) The application is to be treated on and after IP completion day as including an application for a licence under regulation 65 (trade licences).
(3) Paragraph (4) applies where -
(a) an application was made before IP completion day for a licence or authorisation under the Export Control (Russia, Crimea and Sevastopol Sanctions) Order 2014 or the EU Russia Regulations,
(b) the application is for authorisation of an act prohibited by Part 5 (Trade), and
(c) a decision to grant or refuse the application has not been made before IP completion day.
(4) The application is to be treated on and after IP completion day as an application for a licence under regulation 65 (trade licences).