Article 69 Reporting on improvements to the monitoring methodology

1. Each operator or aircraft operator shall regularly check whether the monitoring methodology applied can be improved.

An operator of an installation shall submit to the competent authority for approval a report containing the information referred to in paragraph 2 or 3, where appropriate, by the following deadlines:

(a) for a category A installation, by 30 June every four years;

(b) for a category B installation, by 30 June every two years;

(c) for a category C installation, by 30 June every year.

However, the competent authority may set an alternative date for submission of the report, but no later date than 30 September of the same year.

2. Where the operator does not apply at least the tiers required pursuant to the first subparagraph of Article 26(1) and to Article 41(1), the operator shall provide a justification as to why it is technically not feasible or would incur unreasonable costs to apply the required tiers.

However, where evidence is found that measures needed for reaching those tiers have become technically feasible and do not any more incur unreasonable costs, the operator shall notify the competent authority of appropriate modifications of the monitoring plan in accordance with Article 15, and submit proposals for implementing the related measures and its timing.