Annex VI Minimum content of the monitoring methodology plan

1. General information on the installation:

(a) Information for identifying the installation and the operator, including the Installation identifier used in the Union Registry;

(b) Information identifying the version of the monitoring methodology plan, the date of approval by the competent authority and the date from which it is applicable;

(c) A description of the installation, including in particular a description of the main processes carried out, a list of emissions sources, a flow diagram and a plan of the installation which allow an understanding of the main material and energy flows;

(d) A diagram which contains at least the following information:

- The technical elements of the installation, identifying emissions sources as well as heat producing and consuming units;

- All energy and material flows, in particular the source streams, measurable and non-measurable heat, electricity where relevant, and waste gases;

- The points of measurement and metering devices;