Article 59 Ultra-small emitters: reportable emissions exceeding maximum amount

(1) Subject to paragraph (3), where an installation's reportable emissions in a scheme year for which the installation is an ultra-small emitter exceed the maximum amount, theoperator of the installation is liable to a civil penalty.

(2) The civil penalty is (RE - maximum amount) x CP, where -

RE is the installation'sreportable emissions in the scheme year;

CP is the carbon price for the scheme year.

(3) A civil penalty under this article may be imposed only in respect of -

(a) the first scheme year in an allocation period in which the installation's reportable emissions exceed the maximum amount; and

(b) if the following scheme year is in the same allocation period, that scheme year.