Article 16 Methods for calculating the estimated value of procurement
1. The calculation of the estimated value of a procurement shall be based on the total amount payable, net of VAT, as estimated by the contracting entity, including any form of option and any renewals of the contracts as explicitly set out in the procurement documents.
Where the contracting entity provides for prizes or payments to candidates or tenderers it shall take them into account when calculating the estimated value of the procurement.
2. Where a contracting entity is comprised of separate operational units, account shall be taken of the total estimated value for all the individual operational units.
Notwithstanding the first subparagraph, where a separate operational unit is independently responsible for its procurement or certain categories thereof, the values may be estimated at the level of the unit in question.
3. The choice of the method used to calculate the estimated value of a procurement shall not be made with the intention of excluding it from the scope of this Directive. A procurement shall not be subdivided with the effect of preventing it from falling within the scope of this Directive, unless justified by objective reasons.
4. That estimated value shall be valid at the moment at which the call for competition is sent or, in cases where such call for competition is not foreseen, at the moment at which the contracting entity commences the contract procurement procedure, for instance, where appropriate, by contacting economic operators in relation to the procurement.