Skip to main content
Version date: 26 February 2020 - onwards

Expected value approach (paras. BCZ41-BCZ42)

BCZ41 Some argue that, to better reflect uncertainties in timing and amounts inherent in estimated future cash flows, expected future cash flows should be used in determining value in use. An expected value approach considers all expectations about possible future cash flows instead of the single, most likely, future cash flows.

 

Example

An enterprise estimates that there are two scenarios for future cash flows: a first possibility of future cash flows amounts to 120 with a 40 per cent probability and a second possibility amounts to 80 with a 60 per cent probability.

The most likely future cash flows would be 80 and the expected future cash flows would be 96 (80 × 60% + 120 × 40%).

BCZ42 In most cases, it is likely that budgets/forecasts that are the basis for cash flow projections will reflect a single estimate of future cash flows only. For this reason, IASC decided that an expected value approach should be permitted but not required.