Article 54 Approval of interoperability arrangements

1. An interoperability arrangement shall be subject to the prior approval of the competent authorities of the CCPs involved. The procedure under Article 17 shall apply.

2. The competent authorities shall grant approval of the interoperability arrangement only where the CCPs involved have been authorised to clear under Article 17 or recognised under Article 25 or authorised under a pre-existing national authorisation regime for a period of at least three years, the requirements laid down in Article 52 are met and the technical conditions for clearing transactions under the terms of the arrangement allow for a smooth and orderly functioning of financial markets and the arrangement does not undermine the effectiveness of supervision.